Method Statement wiring cable pulling glanding termination

  The Scope of Work

7.1 Pre-Installation Activities

1)    Ensure that route, areas, ducts to pulled or laid with cables are inspected and approved and clearance is given. Check the availability of proper cables to be used and ensure that these are approved. Ensure that the latest approved drawing shall be used.

2)    Cable drums shall be unloaded at the place of storage or at the installation site. Within the site, the drums shall be transported using high ups, forklifts or power shovels etc. For short distance the cable drums can be shifted by rolled over.

3)    Cables shall be identified with regard to type, size, length etc. and shall be inspected for any physical damage. The cable shall be free from any damages and the ends shall be sealed with caps to prevent the ingress of water during transportation or storage.

4)    Calibration certificate for testing tools & equipment that will be used on site shall be

be submitted along with testing commissioning inspection.

 

7.2  POWER CABLE PULLING WORKS

7.2.1     Cable Pulling and Laying on Cable Ducts

1)    Route measurement shall be done and identification of drum placement points to be marked with peg marking withdrawn numbers prior to material shifting.

2)    All necessary precaution shall be taken while unpacking the cable drums or removal of battens to avoid damage on the cable.

3)    Rolling the drum shall not be allowed for longer distances and shall be ensured only in the direction of arrows marked on the drum.

4)    Check and ensure that the cable ducts or draw pits are clean, free from debris along the route. Duct internal has to be checked by using a correct size of mandrel and clean by using rags tied to a rope and pull back and forth from both ends and check that it is free from any sharp edges. Ensure that the ducts ends are free from sharp edges.

5)    Provide the identification on all ducts as per approved shop drawings to ensure that the correct usage of ducts and the correct members of cables will pass through.

6)    Length of the cable route shall be measured to verify the length of cables required.

7)    Place the cable drums closely as possible to the location where the cables are to be laid.

8)    Wherever necessary, cables have to be applied with approved pulling compound for smooth and easy pulling when entering the cable ducts and cables have to be fixed with bell mouths.

9)    Good communication measures or devices shall be used or maintained for a safe and good cable pulling /laying operation. Two way radios shall be used for communication.

10) Both ends of the cables shall be capped or taped and sealed with heat shrinkable caps and proper identifications shall be provided.

11) All cables inside the cable pit shall be provided with necessary supports as per approved shop drawing.

12) All cable ducts including spares shall be sealed with an approved sealant. Clean all draw pits and place the required cover as per the approved drawings or specifications.

13) Cable pulling and laying has to be done after the inspection and approval of route, areas or ducts are obtained.

 

7.2.2     Cable Pulling and Laying on Trays/ Trunking

1)    Prior to shifting the cable drum to site, check the cable data (ie. cable size, type, number of cores, length, etc.) against approved shop drawing and cable schedule.

2)    Setup the cable stand correctly for even feeding of the cable. Each stand must be in line with each other. Avoid the angle in which the cable will be feed from the reel to the tray.

3)    Jack the cable drum enough to give clearance from the floor slab.

4)    Check the cable containment is ready and the route is clear of any obstruction.

5)    Remove steel binding straps and retaining battens and timbers. Any expose projecting nails must be removed.

6)    Before unreeling cable, double check again cable size, rating and type of the cable inside reel. Confirm the data obtained is as per approved cable schedule/shop drawings.

7)    Inspect the tray/trunking supports. Verify that they are properly fixed.

8)    An approved permanent marker shall be put at each end to identify the cables.

9)    The ends of LV cables are sealed during and after installation. Approved tape or heat shrink tube shall be wrapped around each end of cables.

10) Cable drum has to be supported so that the cable(s) may be unreeled and fed into the tray without being subjected to a reverse bend as the cable is pulled from the reel.

11) Select the correct pulling grip. When selecting a pulling grip, it is extremely important to select a grip of the correct type, size and maximum rated based on the diameter of the cable.

12) Feed the cable to the tray at starting point and pull the rope without unreeling cable on the drum to develop certain pressure between cable and cable grip until it fully grips the cable.

13) All workers assigned at cable reel location shall manually roll drum and unreel cable. During the entire pull, only the person in charge i.e Supervisor or Foreman should give command to workers pulling the cable in order to synchronize with the workers releasing cables at drum end.

14) Pull in the direction that will require the lowest amount of pulling force.

15) After the cable has reached the other end, measure the exact length required for termination to the equipment/panel board. Provide enough allowance (slack) for every termination point before cutting the cable at drum end.

16) Arrange the cable in the tray (follow correct spacing as per approved drawing).

17) Immediately secure the cable to the tray by using cable suitable plastic/aluminium cable cleats/clamps strap/tie. Spacing of cable tie should not be more than 1.5 meter or as closed as required. Cable tie and clips will be used for fixing of smaller size cables running in vertical cable tray and for larger size cables, proper clamps will be used.

18) Measure the required length of cable at drum end to terminating point and unreel it from the drum. Provide adequate slack also for termination.

19) Afterwards, cut the cable from the drum and separate each phase of the cable in preparation for another insulation test.

20) Good communication measures or devices shall be used or maintained for a safe and good cable pulling or laying operation. Two way radios shall be used for communication.

21) Engineer's approval for each and every piece of material used in the process must be obtained prior to execution of the work.

22) Cable pulling and laying has to be done after inspection and approval of installation of cable trays/ trunking are obtained.

23) The work shall be executed according to approved shop drawing.

7.3 CABLE TESTING & COMMISSIONING

1)    At the completion of each cable installation and prior to the connection of any service installation, the insulation resistance and continuity of all cables shall be tested.

2)    An insulation resistance test will be applied between conductors. Test voltage shall be 500VDC on domestic PVC wires and 1000VDC on armoured cables with an approved, calibrated instrument and a continuity test will be applied for each conductor and the readings for each test shall be recorded on the attached test report form.

3)    The insulation test reading should not be less than 1 MΩ and the continuity test reading should not exceed 10M Ω. Thus:

 

Test Voltage (IR): 500VDC/1000VDC

Continuity Test ≤ 10.0 Ω

Insulation Resistance Test ≥ 1.0 MΩ

 

4)    If this not the case, cable must be identified and replaced.

 

7.4 CABLE GLANDING & TERMINATION

·         Check contact surfaces of cable terminations. Brush if necessary and wipe with dry cloth.

·         Check size of the panel enclosure knockouts, both incoming and outgoing cable.

·         Guide cable into connection compartment.

·         Cut cable to length and prepare end for glanding. Adopt reducer rings and fit to the cable.

·         Install cable tags, name as specified in the design electrical schedule in the shop drawings.

·         Electrical panel, light switch and power sockets shall be connected to locking screws according to each terminal (live, neutral, earth) or marked/ identified terminal.

·         Cable glands, cable lugs, crimping tool shall be used during cable termination.

·         Cable lugs bolt screws shall be torque tightened as per required torque figure.

·         Lock terminal screw for wire, must ensure proper tightness and application to each terminal.

·         Wiring devices are identified to the “Distribution Panel” for each ampere schedule and location to which they are connected.

·         Remove the knockout prior to mounting the enclosure. On multiple ring knockouts remove the center section by striking at the point furthest from the tie. Bend the knockout back and forth to break the tie.

·         Use knockout punches where possible to prevent burrs.

·         Use a small magnet to remove any metals shaving from enclosure.

·         If a larger opening is required, remove each additional ring one at a time by prying with a screwdriver and bending back and forth with pliers.

·         Use approved cable clamps (lock nuts) or conduits hubs in the holes to secure the conduit pipes going to panel enclosure and protect the cable and conductors.

·         Carefully, installed the conductors into the raceway to prevent nicks and other damage to insulation.

·         Replace conductors if the insulation is damaged.

·         Assemble the panel interior components and tight the screws and bolts properly.

Separate the phases conductors to two categories as one will be terminated from left side breakers and the other will be terminated to the right side breakers.

·   Separate also the neutral conductors for all circuits which will be terminated to the neutral bus.

·   Separate also the ground conductors for all circuits which will be terminated to the ground bus.

·   Tie each group of phases conductors with cable ties till the first bottom branch circuit breakers.

·   Tie each group of neutral conductors and ground conductors with cable ties till the neutral and ground bars.

·   Adjust the length of each conductor to be able to reach its corresponding circuit breaker, neutral bar or ground bar.

·   Label each conductor as per panel schedule and as per specs.

·   Strip the insulation from the end of each conductor by using approved tools.

·   Don’t allow loose strands of conductor to stick out from terminations.

·   Connect the main conductors to the mechanical lugs of the main circuit breakers.

·   Don’t install more than one conductor under a mechanical lug or termination.

·   Connect the branch circuit conductors to the mechanical lugs of its corresponding branch circuit breakers.

·   Connect the neutral conductors and the ground conductors to the neutral bar and ground bar respectively.

·   Assemble the dead front, the trim and access door of the panel board and securely tight the screws and bolts.

·   Provide circuit directory to the door for listing which breaker provides service for each assigned cable termination.

·   Do the torque as per the requirement.

          Raise request for inspection of cable termination.

 

7.5 INSTALLATION OF DB/SMSB & OTHER ELECTRICAL PANELS: (IF REQUIRED)

7.5.1 Pre-Construction Activities Panels

·          SMDB/DB Panels shall be unloaded with care to avoid any damages. If they are shipped in packs or pallets, each pack of pallet shall be lifted individually with suitable lifting equipment.

·          Hydraulic trolley shall be used for lifting the SMDB in position during installation.

·          A mobile scaffold shall be used for securing the SMDB, DB on the wall and for cable routing and termination.

·          Every precaution shall be taken to preserve their integrity and cleanliness before installation.

·          Store in accordance with manufacturer’s instructions, properly protected from construction activities and weather conditions.

·          The installation of SMDB/DB Panels shall be as per approved shop drawings and coordination drawings.

·          Ensure all required documents (i.e. Associated method statements, shop drawings and material approvals) have been obtained.

·          Before commencing any of the panel board installations, NAT must liaise and get approval from the architect for completion of finishing works as applicable (Plastering and final coat painting).

·           Ensure that Latest and approved schematic diagrams, load schedules, room layouts, section details, installation details etc., should be made available prior to start-up of site work.

·          Necessary certification for plant and electrical equipment must be provided.

·          240V tools if used will be operated through a Residual Current Circuit Breaker (RCCB).

·          Calibration certificate for testing tools & equipment that will be used on site must be submitted.

·          Ensure that the Factory test reports for components of SMDB / DB/ Panels are approved and reviewed upon delivery at site and to be re-tested prior to installation, to ensure a fault free installation.

 

·          The site supervisor/ site Engineer will brief the team on the RAMS for the works and explain the safe system of work and residual risks related to the task to the work force.

·          All the Training records and RAMS shall be kept available on site.

7.5.2 INSTALLATION OF SMDB/DB ELECTRICAL PANELS. (IF REQUIRED)

·          Site Engineer shall check and verify the correct location, position and height of the SMDB/DB Panels to be installed on site with approved shop drawing.

·          SMSB, DB panels/UPS shall be off-loaded using manpower and with the help of trolley and shall be installed on site using a suitable hydraulic trolley.

·          Mark-up the location of the SMDB/DB Panels once the final paint on the wall/floor has been completed.

·          Drill holes on the concrete wall foundation following the depth and position as specified in the approved shop drawing.

·          Clean and remove the dust on the drilled holes.

·          Insert the threaded rod into the hole and ensure its straightness. If needed, provide adequate support to SMSB/DB Panels.

·          Lift and place the SMSB/DB Panels on the concrete wall by manual means or by means of a suitable hydraulic jack.

·          The SMDB/DB Panels shall be positioned in such a way that the entry hole for the supply cable at the metal base frame of the SMDB/DB Panels shall be accessible easily.

·          SMDB/DB panels shall be installed vertically at 90 degree from the horizontal floor level.

·          SMDB/DB Panels shall be fixed on the wall/rigid support frame with bolts and nuts. Insert and tighten at every holding point location of the SMDB/DB Panels, at the torque value of the respective bolts and nuts as provided by the manufacturer.

·          Ensures clearance of not less than 1m in front of SMDB/DB, or as indicated.

·          For flush installation DB’s, all conductors shall terminate behind the board in an adaptable box. For surface mounting, trunking shall be fixed between the board and ceiling or floor level, or conduit run directly into Trunking which prevent correct installation of the Trunking lid. Adequate earth continuity shall be made between the various components.

·          All field wires shall be identified and terminated accordingly with earth connection. Pull wires and/or cables inside the panels.

·          Earth connection shall be tighten properly to connections to assure effective grounding.

·          Terminate the cables inside enclosures by securing the cables to switchboards with gland.

·          Ensure the load schedule in a clear transparent cover within the panels.

·          Protect the SMDB/DB Panels after installation. SMDB/DB Panels shall be thoroughly covered with adequate plastic or paper material to prevent ingress of dust or construction materials.

·          Connect the conductors to the input terminals of MCCB, the neutral conductor to the neutral bar and earthing in the SMDB/DB.

 

·          All wires/cables shall be labeled using approved cable marker and equipment tag no. for easy identification & maintenance.

·          SMSB/DB shall be protected from damage after installation.

    7.5.3 DB PANEL CIRCUIT TERMINATION WORKS:

1)      All the 1st fix & 2nd fix items shall be inspected to ensure they are carried out as per the detailed drawings and fall in requirement of standards as specified.

 

2)      All the wires pulled will be verified through megger (insulation resistance test) for any insulation damages.

3)      Upon confirmation, the wires will be arranged as per individual circuit reference and tagging will be done.

 

4)      Based on the no. of power circuit being used, MCB breakers will be connected to the existing DB or SMDB.

 

5)      Based on the no. of small power circuit being used, ELCB breakers will be connected to the existing DB.

 

6)      Once all the circuit verification & labeling are completed, the termination will be executed.

 

7)      Upon termination completion, the same will be offered for final inspection.

 

8)      The final results of the inspection shall be recorded on form for installation.

 

Mounting Heights for Electrical System:

Isolators   

1250 mm AFFL or as per Site Condition                                                                                                      

Light Switches / Dimmer

1250 mm AFFL

DP Switches   

1250 mm AFFL

Spur Units

As per requirement

13 Ampere Socket Outlets

450 mm AFFL Or As per requirement

Thermostat for A/C                                                   

1250 mm AFFL

 

7.5.4   TESTING AFTER INSPECTION

 

1)      Following checks shall be done to ensure no leakage to earth.

 

A.      Panel board and circuit shall be checked.

B.      All the distribution circuits shall be checked individually.

C.     All the outgoing circuit cabling / wiring shall be checked individually.

D.     Earth leakage circuit breaker (ELCB) trip testing to be done.

E.      Prior to connection, Insulation resistance for all outgoing wiring shall be done.

F.      After termination of cabling / wiring and main cables, the tightness shall be checked for all terminations.

G.     The result of the insulation resistance shall be recorded on form NEC/PRJ/FRM-22/18, Rev No.01, Rev date: 20/08/18

 

2)      Phase sequence check shall be done.

 

3)      Functional check of Distribution Boards shall be done.

 

4)      The final results of the inspection shall be recorded on form.

 

7.5.5 COMMISSIONING OF DISTRIBUTION BOARDS

 

1)      Make sure that the Main Incomer MCCB is in OFF position.

 

2)      Make sure that all the outgoing circuit MCB’s are in OFF position.

 

3)      Ensure the main supply available at corresponding Isolator side.

 

4)      Switch ON the main supply from corresponding Isolator side.

 

5)      Ensure the main supply is available at the main incomer side from the corresponding Isolator side.

 

6)      Check the incoming voltage and make sure that the correct voltage and phase sequence is available at the main incomer side.

 

7)      Switch ON the main MCCB of the panel board.

 

8)      Switch ON the outgoing MCB’s / ELCB’s of the panel board one by one.

 

9)      Check whether the power supply is available at the receiving ends.

 

10)   Ensure that all QA/QC measures have taken during all the activities.

 

7.5.6 TESTING 

Before the start of the final testing & commissioning, make sure to check the following items:

1.    All the installation works are completed as per the drawings & project specification.

2.    All the Power Cables are terminated properly.

3.     Power supply for all the equipment is ready & system is ready to start.

4.    System should be checked as per pre-commissioning checklist.

5.    Panel board and circuit shall be checked.

6.    Prior to connection, continuity for the loop wiring shall be done.

7.    After termination of wiring, the tightness shall be checked for all terminations.

8.    The final results of the inspection shall be recorded on form.

2.       Risk Assessment

All required safety precautionary measures shall be taken before the start of the work and during the execution of this works as per the Risk Assessment provided, refer to the attached risk assessment.

 


Post a Comment