- Materials used are all approved?
- Shop drawings have been approved?
- Installation carried out as per approved details and shop drawings?
- As-built marked on the drawings (red mark). If required?
- Incoming & Out-going cables are pulled?
- Separation form for panels has been checked?
- Fixing of glands for incoming & out-going power cables is properly done?
- Gland earthing is done properly?
- Incoming & Out-going cable lug crimping has been done?
- Incoming & Out-going cable termination has been done properly?
- Neutral & earth cables are connected to relevant links?
- Cables are tagged as per approved Single Line Drawing?
- Height of main incoming cable termination is acceptable?
- REF relay setting is as per Kharamaa requirements?
- Is there any physical or mechanical damage?
- Indicator lamp is in dust-free condition?
- Ratings and settings for each circuit breaker (ACB & MCCM) are as per KM approved panel & SLD?
- Tightness and security for electrical conections has been checked?
- Integrity check for IP Rating & door gasket has been done?
- Is the battery charger directly connected to MV panel?
- Location of current transformer, KWHM & rating have been checked?
- Bus bar size, & labelling has been checked?
- Detail of capacitor bank is as per approved SLD?
- Labelling hase been done as per approved details?