  1.  Materials used are all approved?                                                                                                                                                                                                             
  2. Shop drawings have been approved?                                                                                                                                                                                                     
  3. Installation carried out as per approved details and shop drawings?                                                                                                                                                                                                        
  4. As-built marked on the drawings (red mark). If required?                                                                                                                                                                                              
  5. Incoming & Out-going cables are pulled?                                                                                                                                                                                                              
  6. Separation form for panels has been checked?                                                                                                                                                                                    

                   
  7. Fixing of glands for incoming & out-going power cables is properly done?                                                                                                                                                                                                               
  8. Gland earthing is done properly?                                                                                                                                                                                                             
  9. Incoming & Out-going cable lug crimping has been done?                                                                                                                                                                                                            
  10. Incoming & Out-going cable termination has been done properly?                                                                                                                                                                                                         
  11. Neutral & earth cables are connected to relevant links?                                                                                                                                                                                                 
  12. Cables are tagged as per approved Single Line Drawing?                                                                                                                                                                                                
  13. Height of main incoming cable termination is acceptable?                                                                                                                                                                                                             
  14. REF relay setting is as per Kharamaa requirements?                                                                                                                                                                                                         
  15. Is there any physical or mechanical damage?                                                                                                                                                                                                      
  16. Indicator lamp is in dust-free condition?                                                                                                                                                                                               
  17. Ratings and settings for each circuit breaker (ACB & MCCM) are as per KM approved panel & SLD?                                                                                                                                                                                                              
  18. Tightness and security for electrical conections has been checked?                                                                                                                                                                                                          
  19. Integrity check for IP Rating & door gasket has been done?                                                                                                                                                                                                          
  20. Is the battery charger directly connected to MV panel?                                                                                                                                                  

                                                    
  21. Location of current transformer, KWHM & rating have been checked?                                                                                                                                                                                                     
  22. Bus bar size, & labelling has been checked?                                                                                                                                                                                                         
  23. Detail of capacitor bank is as per approved SLD?                                                                                                                                                                                               
  24. Labelling hase been done as per approved details?                                                                                                                                                                                                          