Method Statement Light fixutes and wiring devices works

The Scope of Work

ACTIVITIES

7.1 LIGHT FIXTURES INSTALLATION:

1)    All lighting circuits shall be installed with a maximum loading of 1800 Watts per circuits.

2)    The only breaker size permitted to be used is 5, 10 And 15 Ampere.

3)    When contactor control is use for lighting circuits, loading may be increased to 7 KW per circuit.

4)    Heat resisting flexible cords of minimum size 1.5 mm2, this included cords insulated with butyl rubber, EP, rubber, silicone rubber or glass fiber, must be used for connection between the ceiling rose and lamp holders for pendant type light fittings.

5)    Where batten lamp holders or enclosed lighting are used, the final connection shall be made by heat resisting cables, or cable cores shall be individually protected by sleeves of suitable heat resisting material e.g. silicon bonded glass braiding.

6)    LED Light fittings shall be supported by direct support from the false ceiling framework (Providing the Ceiling has been designed to withstand the Weight of the Light Fittings).

7)    When using this method, it shall be possible to completely withdraw the light fitting from the ceiling without damage to the ceiling or reducing its rigidity.

8)    Light fittings shall be supported by chain support from the underside of the structural supports.

9)    Each chain shall be secured to the structural support by means of a hook, and at the light fitting, by an approved hook with threaded portion to allow for levelling of the light fitting.

 

7.2 EMERGENCY & EXIT LIGHT INSTALLATION WORKS:

1)    All lighting circuits shall be installed with a maximum loading of 1800 Watts per circuits.

2)    The only breaker size permitted to be used is 5, 10 And 15 Ampere.

3)    Additional exit light & emergency lights circuits shall be connected with the existing light circuits.

4)    Light fittings shall be supported by direct support from the false ceiling framework (Providing the Ceiling has been designed to withstand the Weight of the Light Fittings).

5)    When using this method, it shall be possible to completely withdraw the light fitting from the ceiling without damage to the ceiling or reducing its rigidity.

6)    Light fittings shall be supported by chain support from the underside of the structural supports.

7)    Each chain shall be secured to the structural support by means of a hook, and at the light fitting, by an approved hook with threaded portion to allow for levelling of the light fitting.

8)    Exit light arrow arrangement and direction shall be arranged as per the approved drawings.

 

7.3        WIRING DEVICES INSTALLATION:

1)    13 Ampere switched socket outlets installed in rooms other than kitchens shall be connected using the ring main principle with a maximum of 10 Nos. single socket outlets or 5 nos. double sockets on any one circuit, or one circuit not covering a floor area of greater than 100 m2 whichever is the less.

2)    Twin socket considered as 2 Nos.

3)    Each ring main shall be connected to its own circuit on the distribution board using 4 mm2 P.V.C. cable for the earth conductor and shall be protected by a 30 Ampere MCB.

4)    All conductors shall complete the ring for each circuit, including the earth conductor.

5)    One socket outlet of 15 A rating may be connected to a single phase and neutral circuit wired with 3 x 2.5 mm2 cables, protected by a fuse or circuit breaker not exceeding 16 A.

6)    One special purpose outlet of 15 or 16 Ampere rating may be connected to all single phase and neutral circuit wired with 2.5 mm2 cable, protected by a fuse or circuit breaker not exceeding 16 Ampere. 

7)    No socket outlet shall be mounted within two meters of any tap, sink or basin, in any kitchen, cloakroom, etc. without the special approval.

8)    No spur outlets will be permitted from any ring main wired in 4 mm2 phase conductor and 2.5 mm2 earth conductor.

9)    Joints will not be permitted in any final circuit wiring except at socket outlets, switches, ceiling roses, general accessories and light fittings.

10) A maximum of 6 Nos. spur units may be connected on radial circuit using 4 mm2 P.V.C. cables for the live and neutral connectors and 4 mm2 P.V.C. cables for the earth and shall be protected by 20 Ampere circuit breaker.

11) Each Circuit shall be connected to its own circuit on the distribution board or Sub main Board using Cable sizes 10 mm2   , 6 mm2   ,4 mm2  P.V.C.  Cable for the Power supply and shall be protected by a 30 Ampere MCB as per load requirement.

7.4   ISOLATOR INSTALLATION WORKS: 

1)     Mark the location of isolator on the walls or ceiling. The mounting height of isolator/disconnect switch in the walls are as follows

2)    40A isolators mounting height shall be 1200mm AFFL or as per the site condition.

3)    Fix uni-strut channel support on the wall/ceiling. Ensure that it is fixed properly and rigid.

4)    Fix the isolator/disconnect switch on the unit-strut channel support.  Ensure that it has been fixed vertically and horizontally aligned.

5)    Terminate the incoming and outgoing feeder cable using appropriate wiring 

accessories.

6)    Raise Request for Inspection for isolator/disconnect switches installation.

 

2.       Risk Assessment

All required safety precautionary measures shall be taken before the start of the work and during the execution of this works as per the Risk Assessment provided, refer to the attached risk assessment.