Method statement for electrical + Elv data +cctv + fire alarm + Public address system

 

 

   PROJECT: MEP MODIFICATION WORKS

 

 

    CLIENT:

 

    MAIN CONTRACTOR:

 

    MEP CONTRACTOR: NEC CONTRACTING

 

 

DOCUMENT TITLE

 

METHOD STATEMENT FOR ELECTRICAL/ELV WORKS

 

 

 

 

 

APPROVED BY:

 

 

 

 

 

 

AKNOWLEDGED BY:

 

 

 

REASONS FOR REVISION:

FOR APPROVAL

REVIEWED BY:

 

Projects Manager

 

 

REV. NO.:

0

PREPARED BY:

 

Project Engr.

 

DOCUMENT NUMBER:

 

DATE:

05-06-2023

 

TOTAL PAGES:

           61

 

 

 

 

 

 

 

               

TABLE OF CONTENTS

SL

CONTENTS

PAGE NO.

·          

Tittle Page

1

·          

Table of Contents

1

1.0

Purpose

3

2.0

Scope of Works                                                               

3

3.0

Definitions & Abbreviations

4

4.0

Equipment Delivery, Storage & Handling                         

5

4.1

Material Handling                                                            

5

4.2

Material Storage Area                                                       

5

5.0

Precautions & Safety Program                                         

6

5.1

Coordination of Works                                                       

6

5.2

Permit Requirements                                                         

7

5.3

Communication on Site                                                      

7

5.4

Measuring Equipment to be Used                                        

7

5.4

Safety

7

6.0

References

8

7.0

Work Methodology                                                           

8

7.1

Material Submittal Preparation                                           

8

7.2

Inspection of material and tools deliverables              

9

8.0

Activities                                                                          

9

8.1

Dismantling the existing MEP                            

9

8.2

Containment works

9-13

8.3

Cable pulling works

14-18

8.4

Light installation works

19

8.5

Small power installation works

20

8.6

Isolator installation works

21

8.7

Panel installation works

22-28

8.8

Audio Visual speaker installation works

28-33

8.9

Fire alarm installation works

34-38

8.10

ELV/data installation works

38-49

8.11

CCTV Camera installation works

50-58

9.0

Documentation

58

9.1

System Operation and Maintenance Manual                       

58

10.0

Attachments

59

 

 

 


1.0     PURPOSE:

This method statement is prepared to ensure that the installation, testing and commissioning of ELECTRICAL/ELV system is executed safely and in accordance with the contract requirements. In addition, to ensure that the testing procedure will be in a systematic manner, this will be recorded in accordance to the procedures stated herein.

     

The objectives of the installation, testing and commissioning are:

a.    To verify proper installation of Electrical/ELV system.

b.   To verify the performance of the electrical/ELV system as per the loads, meeting with the specified design intent through a series of tests and adjustments.

 

2.0 SCOPE OF WORKS:

  2.1 Electrical works as per below description:

1.    Modification of existing DB.

2.    Supply and installation of cables and wires.

3.    Removal of existing light fixtures and re-installation of light fittings.

4.    Supply and installation of wiring devices (PVC white finish).

5.    Dismantling and re installation of existing speakers.

6.    Supply and installation of additional Fire Alarm devices.

7.    Supply and installation of 3 nos. of CCTV cameras including configuration of existing system.

8.    Relocation of 5 nos. TV points as per new arrangement.

9.    Integration of new installations to the existing BMS system.

10. Testing and commissioning of electrical works by NEC Contracting.

 

This procedure shall be applied to the inspection, method and criteria for installation work carried out by the electrical department.

 

3.0 DEFINITIONS AND ABBREVATIONS:

 

Client: Mr.

Main Contractor:

Sub-Contractor:

Cold work permit - A document issued for the performance of work where a source of ignition cannot be created. This includes but is not limited to: Drilling, bolting and unbolting, Bending, Threading during the GI ducts / chilled water piping or equipment installation works.

Hot work permit - A document issued for the performance of work where heat or Sparks may be generated, making it possible to ignite flammable liquids, vapors, gas or other combustible materials. This includes but not limited to: burning, welding, grinding, chipping, grit-blasting, use of electrical equipment or internal combustion engines.

May - The word ‘may’ is to be understood as indicating a possible course of action.

Restricted Area - Area over which control is exercised for all movement and operations. Entry is granted only to those people is possession of an official issued pass.

Shall - The word ‘shall’ is to be understood as mandatory

Should - The word ‘should’ is to be understood as strongly recommended.

Work Permit – It’s a formal written statement used to control certain types of work which are identified as potentially hazardous. The permit must be signed by a SB / SE authorized person, provides that the prescribed works, in the manner stated, can be carried out by the holder.

 

4.0 EQUIPMENT DELIVERY, STORAGE & HANDLING

 Deliver, store and handle products using means and methods that will prevent damage, deterioration and comply with manufacturer's written instructions.

 Delivered products to Project site in an undamaged condition and in manufacture's original sealed container or other packing system, complete with labels and instructions for handling, storing & unpacking.

 Storage the electrical equipment in clean areas to protect from any kind of dust & direct sun heat.


4.1 MATERIAL HANDLING

QA/QC Inspector will be responsible in checking and receiving all the materials delivered on site prior to stock in storage area.

All Materials delivered to the site must have all relevant supporting documents complying with the specification of the project. Upon inspection approval it can deliver to storage area, fabrication area or installation area. All Materials delivered on site must have relevant supporting documents, design specification, material specifications and warranty certificates complying with the specification of the project requirements or any relevant supporting documents as deemed necessary for the acceptance of the Engineer. Upon inspection approval it can proceed to Storage Area.

 Equipment & other related accessories will be stored at dry location and will be protected and covered with plastic sheets.

 Equipment and other material which related to the unit installation and material shall be stored on a flat surface in a well-ventilated storage area.

 Materials will be subjected to checks against any defects, deformity, scratches, and specifications adhered to approved material specifications.

 Material will be rejected if not complied with the specification required.

 Prepare Material Delivery to Site Form (MDS) 24 hours prior to the Engineer’s inspection.


4.2 MATERIAL STORAGE AREA

Liquid materials will be stored in the designated CDC MSDS Room. The material shall be sealed or unpacked and free from any foreign materials. In case inspection required, all materials are available in the designated storage area.

 

Storekeeper will be responsible for overlooking all material and accessories while inside Storage Area and always keep the area clean so that the materials will be free from any damages and prevent any accident on Storage Area as well.

Materials are stored in an acceptable and proper manner. All materials not complying Qatar Foundation specification & relevant submittals shall be returned to the suppliers with approval from Project Manager & QA/QC Engineer.

Items found damaged or unsuitable as per the project requirements shall be removed from the site. Until such time the damaged non-compliant material shall be clearly marked and stored separately to prevent any inadvertent use.

Check and ensure that the equipment unit and related accessories are kept neatly.

The Storekeeper, Site Engineer and QA/QC Engineer in the presence of the Consultants shall conduct the material inspection for type, model nos. etc. and quantities as per requirement.

 Work place must ensure proper housekeeping before leaving the activity area, all tools are in proper place and secure the equipment from deterioration or damaged.


5.0 PRECAUTIONS & SAFETY PROGRAM

5.1 COORDINATION OF WORKS

 

Before commencing any work activities coordinate with the Contractor for daily work permit approval.

 

Check and verify all activities if there will be concerned to other Contractors. If there is, inform immediately the person in-charge through a formal letter informing the activities should be taken. Request for Information sheet must submit to the Contractor for coordinating with others Contract Package Contractor.

Inform immediately the Contractor of some work coordination to the other Contractor for proper execution of the activities.

Ensure that all activities must inform other Contractor for proper channeling and safe work free.

Check and verify all activities if there will be concerned to other contractors/disciplines. If there is, inform immediately the person in-charge or through a formal letter informing the activities should be taken.

 

5.2 PERMIT REQUIREMENTS

Work permits shall be obtained prior to any activities being carried-out and work shall commence in accordance indicated in the work permit submitted.

Before performing any overtime work must submit a work permit indicating the activities performing and seek approval first before proceedings to any activities.

Safety Officer will check and advised the Site Engineer to ensure the activities indicated on the work permit will be done with respect to the safety of all personnel, workers and property.

Permits must be submitted by the Contractor before work commences.

Safety Officer will check and advised the Site Engineer to ensure the activities indicated on the work permit will be done with respect to the safety of all personnel, workers and property.


5.3 COMMUNICATION ON SITE

 Site Engineer, supervisors, safety officers and other site personnel shall be provided by mobile phone and walkie-talkie as necessary.

 5.4 MEASURING EQUIPMENT TO BE USED (As necessary and subject for safety personnel acceptance):

Details of equipment and tools to be utilized.

·         Pipe Wrench

·         Adjustable Spanner

·         Grip Plier

·         Hacksaw Frame

·         Steel Cutter

·         Lugs Plier

·         Die set (20,25 sizes)

·         Open / ring Spanner

·         Hammer

·         Chisel

·         Right Angle

·         Wire Cutter

·         File  ( Round / Flat )

·         Safety Belt

·         Knife

·         Line Dori

·         Screwdriver set  (Flat)

·         Screw driver set  (Star)

·         Kalwa (Plier)

·         Plier

·         Spirit Level

·         Tool Box

·         Hilti Drill

·         Rivet Gun

·         Measuring Tape

·         Plump

·         Allen Key

·         Tighter ( Hand tool battery operated with charger )

·         Aluminum Ladder ( 8 Steps )

·         Mobile Scaffoldings

·         Grinding Machine

·         Jigsaw Machine

·         Multi Meter

·         Megger

·         Clamp Meter


5.5 SAFETY:

 5.5.1 All site safety rules and regulations shall be adhered to. Clearance / permit shall be obtained prior to installation/works execution on site.

 5.5.2 All excess materials and tools shall be removed from place of work after completion of equipment final installation inspection.

 

6.0 REFERENCES

Approved drawings.

 Approved Material Transmittal

All letters & email correspondence

Manufacturer Installation Manual/Catalogue (as deemed necessary)

Regulations for the installation of Electrical wiring, Electrical Equipment and Air conditioning Equipment, Edition: December 2016.

Qatar Construction standards (QCS), Edition: 2014, Section: 23

 

7.0 WORK METHODOLOGY

The Sequence of construction works is as followings:

 7.1 Material submittal preparation

 7.2 Inspection of Material and Tools Deliveries

a.    Check all the materials delivered to the site.

b.   Invite Engineer for inspection before transferring the Materials, tools and accessories to working areas.

c.    Prepare a report and mention specifically if there are damages in delivering items.

 

8.0 ACTIVITIES

 8.1 DISMANTLING THE EXISTING MEP SERVICES:

a.     For every activities of dismantling works make sure proper work permit is ready.

b.   All the electrical power supply should switched off or shut off from DB during the works.

c.    Make sure all the equipment/items to be dismantled are free of electrical power supply.


8.2        CONTAINMENT WORKS  

  8.2.1    1st Fix –G.I Rigid Conduiting: 

1)      The entries of GI conduit fittings shall be so designed that reliable water tight joint can be made between the conduit and fittings.

2)      GI conduits shall be so constructed that it is possible bend the conduit easily with the aid of a bending machine and all conduit and conduit fittings shall be of the threaded type.

3)      The minimum size of GI conduit that may be used in electrical installations shall be 20 mm other sizes of conduits shall be limited to the following diameter: 25 mm, 32 mm, 38 mm and 50 mm.

4)      Rigid nonmetallic conduits shall be installed generally in accordance    with the requirements set out for metallic conduits shall allow for the longitudinal expansion and contraction of the conduits.


 8.2.2      1st Fix –PVC Rigid Conduiting:

1)      The entries of PVC conduit fittings shall be so designed that reliable water tight joint can be made between the conduit and fittings.

2)      A Vinyl solvent shall be used for permanent joints and expansion couplers.

3)      PVC conduits shall be so constructed that it is possible bend the conduit easily with the aid of a bending spring and all conduit and conduit fittings shall be of the unthreaded type.

4)      The minimum size of PVC conduit that may be used in electrical installations shall be 20 mm other sizes of conduits shall be limited to the following diameter: 25 mm, 32 mm, 38 mm And 50 mm.

5)      Rigid nonmetallic conduits shall be installed generally in accordance    with the requirements set out for metallic conduits shall allow for the longitudinal expansion and contraction of the conduits.

8.2.3   1st Fix –PVC & GI flexible Conduiting:

1)      Flexible conduits may be employed for connecting electrical motors and other equipment subject to adjustment of position and vibration to the fixed wiring.

2)      PVC & Metallic flexible conduits shall not be used as the sole means of providing earth continuity and a separate earth continuity conductor of appropriate size shall be provided.

3)      Flexible conduits shall only be run exposed and shall be so positioned   that they are not susceptible to mechanical damage. Where necessary flexible conduits shall be adequately supported.

4)      The ends of flexible conduits shall be securely anchored to the fixed conduit or equipment to which it is attached by approved flexible conduit adapters that maintain effective mechanical continuity securely in position without distorting it.

5)      The flexible conduit shall not be used as part of the earth conductor.

6)      A separate earth conductor shall be installed to comply with the same requirements for rigid conduit installations.

7)      The maximum length of a flexible conduit run shall be 2.50 meters.

8)      Where flexible conduit is installed less than 1.50 meters above a floor in a position where it may be easily disturbed or reached, it shall be supported at intervals not exceeding 300 mm.

9)      Except where terminating at motors or at other equipment which requires a free length of flexible conduit to provide for normal movement.

 

8.2.4   GI Cable tray:

1)      A cable tray system shall comprise of a unit or assembly of units or sections and associated fittings, made of metal or other noncombustible materials, forming a rigid structural system.

2)      Cable tray systems include ladders, through channels and solid bottom trays.

3)      Multi core armoured or non armoured cables may be supported by cable trays.

4)      Single core insulated and sheathed cables may also be installed in cable trays.

5)      Cable trays shall not be used in locations where they will be subjected to severe physical damage.

6)      Cable trays shall have adequate strength and rigidity to provide satisfactory support for the cables contained within them.

7)      All sharp edges, burrs and projections shall be removed and the tray shall be finished smooth to prevent injury to cables.

8)      Metallic cable trays shall be adequate protected against corrosion by galvanizing or shall be made of corrosion resistant material.

9)      Nonmetallic cable trays shall be made from polyvinyl chloride or equivalent and shall be fully suitable for continuous service the local climatic conditions.

10)   All cable trays shall be equipped with sides of adequate dimensions. All fittings, bends, tees, employed shall be of substantial sections and of the same quality as the tray itself.

11)   Cable trays shall be installed as complete systems with bends and other accessories.

12)   Each run of cable tray shall be completed before the installation of cables.

13)   Adequate supports shall be provided to prevent stress on cables where they enter or leave the tray.

14)   Where cable tray extends transversely through partitions and walls additional protection in the form of non-combustible covers shall be used.

15)   Sufficient space shall be provided and maintained around cable trays to permit adequate access for installing and maintaining the cables.

16)   Metallic cable trays shall not be used as an earth continuity conductor, although sections shall be bonded using copper links.

17)   The number of multi core cables that may be installed in a ventilated or solid bottom cable tray shall not be greater than the number as per given standard table values.


Method statement for electrical + Elv data +cctv + fire alarm + Public address system

1)      Cable trunking may be employed for housing single core cables at special locations where it is difficult to install conduits.

2)      They may be of metallic or non-metallic construction.

3)      Nonmetallic cable trunking shall be constructed from non-combustible insulation material such as polyvinyl chloride, which shall be fully suitable for use in the conditions.

4)      Metallic cable trunking shall be adequately protected against corrosion by galvanizing or shall be made of corrosion resistant material.

5)      All cable trunking shall be provided with removable covers.

6)      Cable trunking shall, generally, be run exposed and the trunking shall be completely erected before drawing in the cables.

7)      Where adequate means of access is readily available throughout its length, cable trunking may be concealed.

8)      Every entry to trunking shall be so placed as to prevent the ingress of water and all dead ends shall be closed.

9)      Only unbroken lengths of trunking shall be employed for crossing partitions and walls.

10)   Where a common cable trunking is employed for housing both power and communication circuits, or for housing circuits operating at different voltages, the trunking shall be provided with separate compartments       for the different types of circuits.

11)   Cable trunking shall be manufactured from substantial sections to provide adequate strength and rigidity.

12)   All sharp edges, burrs and other projections shall be removed and the trunking finished smooth to prevent injury to cables.

13)   All bends, tees and other accessories of cable trunking shall be of substantial sections and of the same quality as the trunking itself.

14)   Cable trunking shall be securely supported every metre, when run exposed.

15)   The number of single core cables that may be housed in a trunking shall be selected in accordance with the standard table method.

16)   Where a number of cables are bunched in a trunking the current carrying capacity of the cables shall be reduced by using the stipulated grouping factor.

17)   The different sections of the trunking shall be bonded by copper links although the trunking shall not be used as the primary earth conductor.

 

8.3     POWER CABLE PULLING WORKS

8.3.1   Cable Pulling and Laying on Cable Ducts

1)    Route measurement shall be done and identification of drum placement points to be marked with peg marking withdrawn numbers prior to material shifting.

2)    The cable drum shall be transported to the trailer or cable trolley and ensure that the cable drum stands on the flanges and well strapped during the transport stages.

3)    All necessary precaution shall be taken while unpacking the cable drums or removal of battens to avoid damage on the cable.

4)    Rolling the drum shall not be allowed for longer distances and shall be ensured only in the direction of arrows marked on the drum.

5)    Ensure that route, areas, ducts to pulled or laid with cables are inspected and approved and clearance is given. Check the availability of proper cables to be used and ensure that these are approved. Ensure that the latest approved drawing shall be used.

6)    Check and ensure that the cable ducts or draw pits are clean, free from debris along the route. Duct internal has to be checked by using a correct size of mandrel and clean by using rags tied to a rope and pull back and forth from both ends and check that it is free from any sharp edges. Ensure that the ducts ends are free from sharp edges.

7)    Suitable pedestal support with trolley will be installed at intermediate manhole and monitored by personnel located at each manhole during the cable pulling.

8)    Provide the identification on all ducts as per approved shop drawings to ensure that the correct usage of ducts and the correct members of cables will pass through.

9)    Length of the cable route shall be measured to verify the length of cables required.

10) Place the cable drums closely as possible to the location where the cables are to be laid.

11) Wherever necessary, cables have to be applied with approved pulling compound for smooth and easy pulling when entering the cable ducts and cables have to be fixed with bell mouths.

12) During the installation, the drums (especially the big cables) turning or rolling will be slowed down or stop by a wooden friction brakes so as to prevent the turns of the drum from becoming loose and scrapping on the floor. A layer of protective material from the cable will be laid under the drum to act as a barrier to prevent the stones or other material from touching the cables.

13) Good communication measures or devices shall be used or maintained for a safe and good cable pulling /laying operation. Two way radios shall be used for communication.

14) Both ends of the cables shall be capped or taped and sealed with heat shrinkable caps and proper identifications shall be provided.

15) All cables inside the cable pit shall be provided with necessary supports as per approved shop drawing.

16) All cable ducts including spares shall be sealed with an approved sealant. Clean all draw pits and place the required cover as per the approved drawings or specifications.

17) Cable pulling and laying has to be done after the inspection and approval of route, areas or ducts are obtained.

 

8.3.2   Cable Pulling and Laying on Trench

1)    Ensure that route, areas or trench to be pulled or laid with cables are inspected, approved and clearance is given. Check the availability of proper cables to used and ensure that these are approved. Ensure that the latest approved drawing shall be used.

2)    Check and ensure that the cable ducts/draw pits are clean, free from debris along the route. Trench clearance shall be obtained from consultant.

3)    Length of the cable route shall be measured to verify the length of cables required.

4)    Place the cable drums closely as possible to the location where the cables are to be laid.

5)    Approved dune sand shall be laid on the bedding of the trench prior to cable pulling/laying if called for in specifications.

6)    Cable rollers shall be placed at approximate distance between rollers by 1.0 meter- 1.5 meters and fixed well along the route. Check each roller if it is rolling smoothly, apply WD40 or grease as required. Top ensure the stability of each roller laid on loose sand bedding, a wooden pieces or plastic sheets are to be placed under the base of each roller.

7)    Wherever necessary, cables have to be applied with approved pulling compound for smooth and easy pulling when entering the cable ducts and cable to be fixed with bell mouths.

8)    During the installation, the drums (especially the big cables) turning or rolling will be slowed down or stop by a wooden friction brake so as to prevent the turns of the drum from becoming loose and scrapping on the floor. A layer of protective material from the cable will be laid under the drum to act as a barrier to prevent the stones or other material from touching the cables.

9)    Good communication measures or devices shall be used or maintained for a safe and good cable pulling or laying operation. Two-way radios shall be used for communication.

10) Both ends of the cables shall be capped or taped and sealed with heat shrinkable caps and proper identifications shall be provided.

11) The laid cables are to be arranged/dressed, proper clearance to be maintained and tied with approved cable ties.

12) Trench shall be backfilled by sand or soil, step by step as mentioned in the approved drawings and specifications. Cable tiles, warning tapes, route markers shall be installed as per the contract requirement by using an approved material and approved method by civil contractor.

13) Inspection shall be carried out by competent authority by notifying through inspection request form and checklist shall be filled up and signed.

14) Engineer's approval for each and every piece of material used in the process must be obtained prior to execution of the work.

15) Cable pulling and laying has to be done after inspection and approval of route, areas and trench are obtained.

16) The work shall be executed according to approved shop drawing.

 

8.3.3   Cable Pulling and Laying on Trays/ Trunking

1)    Prior to shifting the cable drum to site, check the cable data (ie. cable size, type, number of cores, length, etc.) against approved shop drawing and cable schedule.

2)    Setup the cable stand correctly for even feeding of the cable. Each stand must be in line with each other. Avoid the angle in which the cable will be feed from the reel to the tray.

3)    Jack the cable drum enough to give clearance from the floor slab.

4)    Check the cable containment is ready and the route is clear of any obstruction.

5)    Remove steel binding straps and retaining battens and timbers. Any expose projecting nails must be removed.

6)    Before unreeling cable, double check again cable size, rating and type of the cable inside reel. Confirm the data obtained is as per approved cable schedule/shop drawings.

7)    Inspect the tray/trunking supports. Verify that they are properly fixed.

8)    An approved permanent marker shall be put at each end to identify the cables.

9)    The ends of LV cables are sealed during and after installation. Approved tape or heat shrink tube shall be wrapped around each end of cables.

10) Cable drum has to be supported so that the cable(s) may be unreeled and fed into the tray without being subjected to a reverse bend as the cable is pulled from the reel.

11) Select the correct pulling grip. When selecting a pulling grip, it is extremely important to select a grip of the correct type, size and maximum rated based on the diameter of the cable.

12) Feed the cable to the tray at starting point and pull the rope without unreeling cable on the drum to develop certain pressure between cable and cable grip until it fully grips the cable.

13) All workers assigned at cable reel location shall manually roll drum and unreel cable. During the entire pull, only the person in charge i.e Supervisor or Foreman should give command to workers pulling the cable in order to synchronize with the workers releasing cables at drum end.

14) Pull in the direction that will require the lowest amount of pulling force.

15) After the cable has reached the other end, measure the exact length required for termination to the equipment/panel board. Provide enough allowance (slack) for every termination point before cutting the cable at drum end.

16) Arrange the cable in the tray (follow correct spacing as per approved drawing).

17) Immediately secure the cable to the tray by using cable suitable plastic/aluminium cable cleats/clamps strap/tie. Spacing of cable tie should not be more than 1.5 meter or as closed as required. Cable tie and clips will be used for fixing of smaller size cables running in vertical cable tray and for larger size cables, proper clamps will be used.

18) Measure the required length of cable at drum end to terminating point and unreel it from the drum. Provide adequate slack also for termination.

19) Afterwards, cut the cable from the drum and separate each phase of the cable in preparation for another insulation test.

20) Good communication measures or devices shall be used or maintained for a safe and good cable pulling or laying operation. Two way radios shall be used for communication.

21) Engineer's approval for each and every piece of material used in the process must be obtained prior to execution of the work.

22) Cable pulling and laying has to be done after inspection and approval of installation of cable trays/ trunking are obtained.

23) The work shall be executed according to approved shop drawing.

8.3.4 CABLE TESTING & COMMISSIONING

1)    At the completion of each cable installation and prior to the connection of any service installation, the insulation resistance and continuity of all cables shall be tested.

2)    An insulation resistance test will be applied between conductors. Test voltage shall be 500VDC on domestic PVC wires and 1000VDC on armoured cables with an approved, calibrated instrument and a continuity test will be applied for each conductor and the readings for each test shall be recorded on the attached test report form.

3)    The insulation test reading should not be less than 1 MΩ and the continuity test reading should not exceed 10M Ω. Thus:

 

Test Voltage (IR): 500VDC/1000VDC

Continuity Test ≤ 10.0 Ω

Insulation Resistance Test ≥ 1.0 MΩ

 

4)    If this not the case, cable must be identified and replaced.


8.4     LIGHTING INSTALLATION:

8.4.1   LIGHT FIXTURES INSTALLATION:

1)    All lighting circuits shall be installed with a maximum loading of 1800 Watts per circuits.

2)    The only breaker size permitted to be used is 5, 10 And 15 Ampere.

3)    When contactor control is use for lighting circuits, loading may be increased to 7 KW per circuit.

4)    Heat resisting flexible cords of minimum size 1.5 mm2, this included cords insulated with butyl rubber, EP, rubber, silicone rubber or glass fiber, must be used for connection between the ceiling rose and lamp holders for pendant type light fittings.

5)    Where batten lamp holders or enclosed lighting are used, the final connection shall be made by heat resisting cables, or cable cores shall be individually protected by sleeves of suitable heat resisting material e.g. silicon bonded glass braiding.

6)    LED Light fittings shall be supported by direct support from the false ceiling framework (Providing the Ceiling has been designed to withstand the Weight of the Light Fittings).

7)    When using this method it shall be possible to completely withdraw the light fitting from the ceiling without damage to the ceiling or reducing its rigidity.

8)    Light fittings shall be supported by chain support from the underside of the structural supports.

9)    Each chain shall be secured to the structural support by means of a hook, and at the light fitting, by an approved hook with threaded portion to allow for leveling of the light fitting.

       8.4.2 EMERGENCY & EXIT LIGHT INSTALLATION WORKS:

1)    All lighting circuits shall be installed with a maximum loading of 1800 Watts per circuits.

2)    The only breaker size permitted to be used is 5, 10 And 15 Ampere.

3)    Additional exit light & emergency lights circuits shall be connected with the existing light circuits.

4)    Light fittings shall be supported by direct support from the false ceiling framework (Providing the Ceiling has been designed to withstand the Weight of the Light Fittings).

5)    When using this method it shall be possible to completely withdraw the light fitting from the ceiling without damage to the ceiling or reducing its rigidity.

6)    Light fittings shall be supported by chain support from the underside of the structural supports.

7)    Each chain shall be secured to the structural support by means of a hook, and at the light fitting, by an approved hook with threaded portion to allow for leveling of the light fitting.

8)    Exit light arrow arrangement and direction shall be arranged as per the approved drawings.

 

8.5     SMALL POWER INSTALLATION:

1)    13 Ampere switched socket outlets installed in rooms other than kitchens shall be connected using the ring main principle with a maximum of 10 Nos. single socket outlets or 5 nos. double sockets on any one circuit, or one circuit not covering a floor area of greater than 100 m2 whichever is the less.

2)    Twin socket considered as 2 Nos.

3)    Each ring main shall be connected to its own circuit on the distribution board using 4 mm2 P.V.C. cable for the earth conductor and shall be protected by a 30 Ampere MCB.

4)    All conductors shall complete the ring for each circuit, including the earth conductor.

5)    One socket outlet of 15 A rating may be connected to a single phase and neutral circuit wired with 3 x 2.5 mm2 cables, protected by a fuse or circuit breaker not exceeding 16 A.

6)    One special purpose outlet of 15 or 16 Ampere rating may be connected to all single phase and neutral circuit wired with 2.5 mm2 cable, protected by a fuse or circuit breaker not exceeding 16 Ampere. 

7)    No socket outlet shall be mounted within two meters of any tap, sink or basin, in any kitchen, cloakroom, etc. without the special approval.

8)    No spur outlets will be permitted from any ring main wired in 4 mm2 phase conductor and 2.5 mm2 earth conductor.

9)    Joints will not be permitted in any final circuit wiring except at socket outlets, switches, ceiling roses, general accessories and light fittings.

10) 1 No.Split A/C unit in air conditioning system shall be connected to its own 30 Ampere TPN isolator mounted adjacent to the unit.

11) A maximum of 6 Nos. spur units may be connected on radial circuit using 4 mm2 P.V.C. cables for the live and neutral connectors and 4 mm2 P.V.C. cables for the earth and shall be protected by 20 Ampere circuit breaker.

12) 30 Ampere DP Switches shall be installed in designated area for split AC and shall be connected using with 3 x 6 mm2 cables on any one circuit.

13) Power Supply shall be given connected through Weather proof Isolators from DB /SMDB for Split AC, ducted Split AC and FAHU Unit.

14) Each Circuit shall be connected to its own circuit on the distribution board or Sub main Board using Cable sizes 10 mm2   , 6 mm2   ,4 mm2  P.V.C.  Cable for the Power supply and shall be protected by a 30 Ampere MCB as per load requirement.

15) Spur Units / Isolators for indoor unit will be connected from the same circuit wired in 4 mm2 phase/neutral conductor and 4 mm2 earth conductor from Outdoor Unit - WP Isolator. (If required)

16) 1 No. Split AC unit in air conditioning system shall be connected to its own 30 Ampere DP isolator mounted adjacent to the unit.

  8.6    ISOLATOR INSTALLATION WORKS: 

1)     Mark the location of isolator on the walls or ceiling. The mounting height of isolator/disconnect switch in the walls are as follows

2)    40A isolators mounting height shall be 1500mm AFFL from the Top. and 200A, mounting height shall be 1500mm A.F.F.L. from the top or as per the site condition.

3)    Fix uni-strut channel support on the wall. Ensure that it is fixed properly and rigid.

4)    Fix the isolator/disconnect switch on the unit-strut channel support.  Ensure that it 

has been fixed vertically and horizontally aligned.

5)    Terminate the incoming and outgoing feeder cable using appropriate wiring 

accessories.

6)    Raise Request for Inspection for isolator/disconnect switches installation.

7)    Before relocation of isolators, QNB Maintenance team shall be informed and requested for power switch off of main source of isolator and equipment power supply to arrange accordingly.

 

8.7 INSTALLATION OF DB/SMSB & OTHER ELECTRICAL PANELS: (IF REQUIRED)

8.7.1 Pre-Construction Activities Panels

SMDB/DB Panels shall be unloaded with care to avoid any damages. If they are shipped in packs or pallets, each pack of pallet shall be lifted individually with suitable lifting equipment.

Hydraulic trolley shall be used for lifting the SMDB in position during installation.

 A mobile scaffold shall be used for securing the SMDB, DB on the wall and for cable routing and termination.

 Every precaution shall be taken to preserve their integrity and cleanliness before installation.

Store in accordance with manufacturer’s instructions, properly protected from construction activities and weather conditions.

 

The installation of SMDB/DB Panels shall be as per approved shop drawings and coordination drawings.

Ensure all required documents (i.e. Associated method statements, shop drawings and material approvals) have been obtained.

Before commencing any of the panel board installations, NAT must liaise and get approval from the architect for completion of finishing works as applicable (Plastering and final coat painting).

Ensure that Latest and approved schematic diagrams, load schedules, room layouts, section details, installation details etc., should be made available prior to start-up of site work.

 Necessary certification for plant and electrical equipment must be provided.

 240V tools if used will be operated through a Residual Current Circuit Breaker (RCCB).

Calibration certificate for testing tools & equipment that will be used on site must be submitted.

 

·          Ensure that the Factory test reports for components of SMDB / DB/ Panels are approved and reviewed upon delivery at site and to be re-tested prior to installation, to ensure a fault free installation.

The site supervisor/ site Engineer will brief the team on the RAMS for the works and explain the safe system of work and residual risks related to the task to the work force.

All the Training records and RAMS shall be kept available on site.


8.7.2 INSTALLATION OF SMDB/DB ELECTRICAL PANELS. (IF REQUIRED)

 Site Engineer shall check and verify the correct location, position and height of the SMDB/DB Panels to be installed on site with approved shop drawing.

SMSB, DB panels/UPS shall be off-loaded using manpower and with the help of trolley and shall be installed on site using a suitable hydraulic trolley.

Mark-up the location of the SMDB/DB Panels once the final paint on the wall/floor has been completed.

 Drill holes on the concrete wall foundation following the depth and position as specified in the approved shop drawing.

Clean and remove the dust on the drilled holes.

Insert the threaded rod into the hole and ensure its straightness. If needed, provide adequate support to SMSB/DB Panels.

Lift and place the SMSB/DB Panels on the concrete wall by manual means or by means of a suitable hydraulic jack.

 The SMDB/DB Panels shall be positioned in such a way that the entry hole for the supply cable at the metal base frame of the SMDB/DB Panels shall be accessible easily.

SMDB/DB panels shall be installed vertically at 90 degree from the horizontal floor level.

SMDB/DB Panels shall be fixed on the wall/rigid support frame with bolts and nuts. Insert and tighten at every holding point location of the SMDB/DB Panels, at the torque value of the respective bolts and nuts as provided by the manufacturer.

Ensures clearance of not less than 1m in front of SMDB/DB, or as indicated.

For flush installation DB’s, all conductors shall terminate behind the board in an adaptable box. For surface mounting, trunking shall be fixed between the board and ceiling or floor level, or conduit run directly into Trunking which prevent correct installation of the Trunking lid. Adequate earth continuity shall be made between the various components.

All field wires shall be identified and terminated accordingly with earth connection. Pull wires and/or cables inside the panels.

 Earth connection shall be tighten properly to connections to assure effective grounding.

Terminate the cables inside enclosures by securing the cables to switchboards with gland.

 Ensure the load schedule in a clear transparent cover within the panels.

Protect the SMDB/DB Panels after installation. SMDB/DB Panels shall be thoroughly covered with adequate plastic or paper material to prevent ingress of dust or construction materials.

Connect the conductors to the input terminals of MCCB, the neutral conductor to the neutral bar and earthing in the SMDB/DB.

All wires/cables shall be labeled using approved cable marker and equipment tag no. for easy identification & maintenance.

SMSB/DB shall be protected from damage after installation.

 

    8.7.3 DB PANEL CIRCUIT TERMINATION WORKS:

1)      All the 1st fix & 2nd fix items shall be inspected to ensure they are carried out as per the detailed drawings and fall in requirement of standards as specified.

2)      All the wires pulled will be verified through megger (insulation resistance test) for any insulation damages.

3)      Upon confirmation, the wires will be arranged as per individual circuit reference and tagging will be done.

4)      Based on the no. of power circuit being used, MCB breakers will be connected to the existing DB or SMDB.

5)      Based on the no. of small power circuit being used, ELCB breakers will be connected to the existing DB.

6)      Once all the circuit verification & labeling are completed, the termination will be executed.

7)      Upon termination completion, the same will be offered for final inspection.

8)      The final results of the inspection shall be recorded on form for installation.

Mounting Heights for Electrical System:

Isolators   

1250 mm AFFL or as per Site Condition                                                                                                      

Light Switches / Dimmer

1250 mm AFFL

DP Switches   

1250 mm AFFL

Spur Units

As per requirement

13 Ampere Socket Outlets

450 mm AFFL Or As per requirement

Thermostat for A/C                                                   

1250 mm AFFL

 

8.7.4   TESTING AFTER INSPECTION

1)      Following checks shall be done to ensure no leakage to earth.

A.     Panel board and circuit shall be checked.

B.     All the distribution circuits shall be checked individually.

C.     All the outgoing circuit cabling / wiring shall be checked individually.

D.     Earth leakage circuit breaker (ELCB) trip testing to be done.

E.      Prior to connection, Insulation resistance for all outgoing wiring shall be done.

F.      After termination of cabling / wiring and main cables, the tightness shall be checked for all terminations.

G.     The result of the insulation resistance shall be recorded on form FRM-22/18, Rev No.01

2)      Phase sequence check shall be done.

3)      Functional check of Distribution Boards shall be done.

4)      The final results of the inspection shall be recorded on form for installation.

8.7.5 COMMISSIONING OF DISTRIBUTION BOARDS

1)      Make sure that the Main Incomer MCCB is in OFF position.

2)      Make sure that all the outgoing circuit MCB’s are in OFF position.

3)      Ensure the main supply available at corresponding Isolator side.

4)      Switch ON the main supply from corresponding Isolator side.

5)      Ensure the main supply is available at the main incomer side from the corresponding Isolator side.

6)      Check the incoming voltage and make sure that the correct voltage and phase sequence is available at the main incomer side.

7)      Switch ON the main MCCB of the panel board.

8)      Switch ON the outgoing MCB’s / ELCB’s of the panel board one by one.

9)      Check whether the power supply is available at the receiving ends.

10)   Ensure that all QA/QC measures have taken during all the activities.


8.7.6 TESTING

Before the start of the final testing & commissioning, make sure to check the following items:

1.    All the installation works are completed as per the drawings & project specification.

2.    All the Power Cables are terminated properly.

3.     Power supply for all the equipment is ready & system is ready to start.

4.    System should be checked as per pre-commissioning checklist.

5.    Panel board and circuit shall be checked.

6.    Prior to connection, continuity for the loop wiring shall be done.

7.    After termination of wiring, the tightness shall be checked for all terminations.

8.    The final results of the inspection shall be recorded on form  for installation

 

8.8 INSTALLATION OF SPEAKER AV SYSTEM

Audio Visual speakers are specifically designed for use in buildings where performance of systems for any function or ceremony or for background music to be the requirement.

 

8.8.1 Open Ceiling Installation

The public address speaker must be suspended from the back of the can in both open ceiling and ceiling tile applications, using either the 3 pendant mount tabs or the 3/8” threaded rigging point. To prevent rattles, rotate the 4 mounting tabs towards the can, then tighten the mounting tab screws.

 

8.8.2 Ceiling Tile Installation

Step 1: Cut the Hole (Figure 5) Cut out the hole by tracing the cardboard template or with a circular cutter set to the appropriate cut out size. If the wire has been pre-installed, pull the wiring through the cut out hole.

 

Step 2: Install C-Ring and Tile Rails for suspended ceiling installations, insert the C-ring through the hole cut in the ceiling tile. Place the C-ring around the hole with the tabs located. Insert the tile rails through the cut hole in the ceiling tile. Snap the two rails into the two tabs in the C-ring and align the rails so that the ends extend over the T-channel grid on the side of the tile. Secure the rails onto the C-ring tabs by inserting a screw though each tab into the rail.

 

Step 3: Terminal Block

 The unit has a three-way terminal block with screw connections suitable for loop-through wiring. Four primary taps are provided on the matching transformer to allow selection of nominal full-power, half-power, quarter-power or eighth power radiation (i.e. in 3 dB steps).

Attach Wiring to the Ceramic Connector (Figure 7) Insert the bare end of wire into the appropriate connector terminals as described below and screw down the hold-down screw until tight, using a small screwdriver.

 

Step 4: Mount the Speaker into the Ceiling (Figure 8) Push the speaker into the ceiling hole until the front baffle rim is flush with the ceiling. Tighten the mounting tabs by turning the screw clockwise until the speaker is secure. Please note that the first clockwise quarter turn rotates the attachment tabs outward. The remaining turns tighten the tabs down onto the back of the ceiling surface (see Figure 9).

 

Note:- If 3/8” threaded rod is to be used in a ceiling tile installation, the threaded rod must be installed to the threaded rigging point before installing into the ceiling.

For each attachment screw, first turn one half turn counter clockwise to release the counting tab from its guide.

The assembly is quickly installed into a hole in the ceiling cavity. A separate mounting ring, secured by three integral spring-loaded ceiling locking clamps (for ceilings and wall boards from 9 to 25 mm thick) holds it in place. The clamps are provided with protective rubbers to avoid damaging soft ceiling material. A circular template for marking a 196 mm (7.7 in) diameter hole is included with the loudspeaker. The loudspeaker unit is held in the mounting ring with a bayonet fitting.

After completion of the landing of the speaker cables, the cables will be tested with a standard industrial insulation tester. The tests shall be conducted to check and or verify for short circuits between conductors and the outer sheath. If each core cannot be identified, they will be phased to determine each core at both ends & will be appropriately marked.

Ensure that the speakers installed as per the approved IFC drawings.
Ensure that the wiring termination for the public address system is complete & correct polarity is maintained for all field devices.
Ensure that the speaker cables are pretested for continuity before termination.
Ensure the availability of power supply to the voice evacuation panels.
Verify and double-check all field devices are appropriately supported & secured.
Check and verify for proper identification on of all Public address system.


8.9 FIRE ALARM SYSTEM

8.9.1 Smoke Detector & Heat Detector

·         Care shall be taken while handling detectors.

·         Ensure that the mobile scaffolding used for installation is approved.

·         Ensure that the proper hand tools are used for avoiding any damages to devices or technician.

·         Notes:

·         Break off plastic tab where indicated to engage locking mechanism.

·         Once locking mechanism is engaged, you must insert a flat-head screwdriver in slot indicated to release the detector from the base.

·         Use the slotted hole indicated for the first screw when mounting.

·         All detectors shall be installed with dust covers. It is important that the dust covers shall be removed only prior to testing & commissioning.

·         Use a small screwdriver or pen to set the switches.

 

·         Double-check the location of the sensor base and its address before proceeding to electrical

·         To lock detector/sensor into base, turn unit until the locking tab clicks into place.

·         To unlock detector/sensor, insert the blade of a screwdriver into this slot and then pull down on handle. This action allows the detector/sensor to be turned and removed. 

 

8.9.2 Manual Call Point

·         Care shall be taken while handling detectors.

·         Ensure that the mobile scaffolding used for installation is approved.

·         Ensure that the proper hand tools are used for avoiding any damages to devices or technician.

·         Fix the Back box to a flat vertical surface using a mounting holes provided.

·         The Loop cable may be connected to the terminals provided.

·         Manual call point shall be located in the Entrance, normal path of Exit and distributed in the protected area as per the approved shop drawing.

·         Manual Call point should be install at the height of 1.2 M from the finished floor level.

·         Testing the Manual Call point may be carried out either by Pull Down the element or by using the key.

·         Ensure that Manual Call Point are unobstructed and readily accessible

·         Use a small screwdriver or pen to set the switches.

·         Double-check the location of the manual call point and its address before proceeding to electrical installation.

 

8.9.3 Installation of Wall Mounted Sounders / Horn Strobes

·         Care shall be taken while handling devices.

·         Ensure that the mobile scaffolding used for installation is approved.

·         Ensure that the proper hand tools are used for avoiding

·         Install horn strobes on flush mounted back boxes with the device operating mechanism concealed behind the back box as shown on the shop drawings.

·         Make the necessary termination / connection based on the termination instruction provided witthe device. Connect the loop cables to the sounder terminal block observing polarity.    

Terminals are provided for the wiring the horn and strobe of these A/Vs to separate NACs.

Operation of the horn and strobe is not separately controlled when they are both wired to same NAC.

·         The Horn strobe must be connected to signal circuits which output a constant (not pulsed) 24V dc voltage.

·         Ensure that End of Line resistor (provided in the panel’s accessory pack) must be connected at the end of the NAC circuit to allow the wiring to be monitored.

8.9.4 Inspection and Testing

·         After completion of installation, the Fire Detection and Alarm System will be inspected in accordance with the approved drawings, codes, specifications and this method statement.

·         Identification/ labelling shall be inspected prior to subjecting the system for inspection.

·         All the 1st fix & 2nd fix items shall be inspected to ensure they are carried out as per the detailed shop drawings and fall in requirement of standards as specified.

·         All the wires/cables pulled will be verified through Multi meter for Continuity test.

·         Upon confirmation, the wires will be arranged as per individual circuit reference and tagging will be done based on the loop no. incoming & outgoing cable for each detector point.

·         Once all the circuit verification & labelling are completed, the termination will be executed.

·         During the ceiling closure, fire alarm cable shall be ready to drop down after false ceiling works.

·         Upon termination completion, the same will be offered for final inspection.

·         Reprogramming of fire alarm and recommended testing in accordance with QCCD requirement testing commissioning shall be done by fire alarm specialist.

 

Mounting Heights of Fire Alarm Devices:

1.    Fire alarm control panel                     :     2200 mm AFFL from Top of panel

2.    Pull station (Manual Call Point)              :    1250 mm AFFL

3.    Interface Module                         :     As per req. on AFC

4.    Sounder Horn & Strobe light              :           2100 mm AFFL

5.    Smoke detector                                   :      On False ceiling

6.    Smoke detector (AFC)                  :     Above False ceiling

7.    Remote LED Indicator                             :     On False ceiling

 

8.10   INSTALLATION OF ELV/DATA SYSTEM

8.10.1 CAT6A CABLES

·         Pull rope in conduit is tied to pulling spring with insulation tape & pulling spring is drawn inside the conduit.

·         The required Nos. of cable is tied to the pulling spring with insulation tape and drawn inside the conduit.

·         Cable will be pulled gradually meter by meter, by one person, while another person on other end will be feeding the cable in pipe continuously. If any hindrance is experienced while feeding the cable, the pulling person will be told to stop.

·         The cable will be pulled gradually with minimum force. If cable pulling is too tight we check for damage in pipes, or if lengths exceeds 30 meter or if more than 2 nos. of 90 deg. bend are used.

·         Not more than 3 Nos. of Data cable to be pulled in 25mm conduit or as specified in the approved IFC/Shop drawings.

·         Care should be taken not to draw the cable with any kink, twist or damage. Such cables should be cancelled.

·         For Trunking, the cable is laid in a neat and order fashion, with ample of space for closing the cover.

·         When laying cables in tray, cable will be symmetrically arranged and cable ties will be used at every 60 cm.

·         Additional Cat6a Cable loop i.e., 5-10 meters shall be left at both ends.

·         All Sleeve opening shall be sealed after the cable pulling.

 

8.10.2 TERMINATION OF CAT 6A CABLES

Start with clean hands, cable, parts, tools to avoid electrical irregularities in the finished product.

Cable Preparation

Copper cables should only be prepared and connected using suitable tools. If, for example, a knife or an unsuitable stripping tool is used when stripping the cables, there is a risk that the wires in the cable may be damaged or their insulation cut. If this is the case, it is highly likely that shielding, short-circuits or other sources of error are then caused. It is also important to use a side cutter that allows the wires to be cut cleanly and flush. You should make sure that all modules or plugs, regardless of their design, are connected cleanly and carefully.

 

 

 

Cat 6A Key Connect Modular Jack

·         Cable Preparation:

a)  Cut off approx. a 2 in. (5 cm) portion of the jacket.

b)  Slit jacket approx. 4 in. (10 cm) with ripcord, or use a standard slitting tool; Cut off jacket at the bottom of slit.

c)  Cut the Ripcord, if any; fold back the aluminum tape over the jacket.

d)  Keep 0.5 in. (1 cm) of the aluminum-polyester screen; Wind the drain wire around the aluminum foil.

e)  Remove the PET tape that recovers the 4 twisted pair.

f)   Cut off cross-web.

·         Wire Guide Preparation:

a)    For TIA568-B configuration, align pairs as shown;

 

b)    Push the Wire Guide against the Jacket; untwist the wire pairs; Split the bonded pairs with the Cable.

c)    Follow the color code that is on the side of the jack.

d)    Prepare to terminate the pairs by positioning the end of the skinned jacket very close to the back end of the jack.

e)    Cut the extra wires with a flush cutter. The tips of the wires should protrude no more than 1/16 in (0.5mm).

·         Module Termination:

a.       Align the Wire Guide’s arrows with the Module arrows.

b.       Close the jaw until it clicks into place; Slide the shielding lug close to the jacket.

c.        Wrap the cable tie around the shielding lug and position it as shown.


·         Module Installation in Patch Panel:

a.    To insert, engage the bottom of the module in the opening

b.   Then press the top latch and pivot the Module as shown

 

8.10.3 TESTING OF CAT6A CABLES

·         Copper cabling transmission performance depends on cable characteristics, connecting hardware, patch cords and cross-connect wiring, the total number of connections, and the care with which they are installed and maintained.

·         The following channel test configuration should be used by system designers and users of data communications systems to verify the performance of the overall copper channel.

·         Channel performance is the most critical to the end user, as this is how their network will perform. The channel includes up to 90 m (295 ft.) of horizontal cable, a work area equipment cord, a telecommunications outlet/ connector, an optional transition/consolidation connector, and two connections in the telecommunications room.

·         2TIA/EIA-568B.2-1 recommends and ISO 11801 requires that the consolidation point be located at least 5 m (16.4 ft.) from the telecommunications room to reduce the effect of multiple connections in close proximity on NEXT loss and return loss.

·         Per the TIA standard, the total length of equipment cords, patch cords or jumpers and work area cords shall not be more than 10 m (32.8 ft.). If total patch cords are longer than 10 meters, the entire channel length must be de-rated by the length exceeding 10 meters depending either by 20% or 50% depending on the patch cord cable type used.

·         The connections to the equipment at each end of the channel are not included in the channel definition. The channel definition does not apply to those cases where the horizontal cabling is cross-connected to the backbone cabling. It has evaluated the Fluke DTX-1800 Series Digital Cable Analyzer and approves the use of this tester for the certification of installed 10 GB/s cabling channels.

·         In order to verify that the installed cabling will meet or exceed the performance requirements of the designated classification defined in the IEEE 802.3an Standard, it is important that the following steps are followed.

 

 

Channel Testing

1.    Verify that your Fluke tester has the most up-to-date software.

 

2.    Perform a Set Reference procedure in the special functions prior to testing. Fluke Networks recommends that a Set Reference procedure be performed every 30 days to ensure the maximum accuracy of the test results. For detailed instructions on Set

 

Note: Fluke Networks also recommends factory calibration once a year to ensure that the test tool meets or exceeds the published accuracy specifications.

 

3.    Select the Fluke Channel Adapter (# DTX-CHA001A (AxTalk)) and attach them to the DTX-1800 Series Main and Remote unit.

Select from the following Fluke Autotests:

-          10GBASE-T

-          TIA Category 6ACh.h

-          TIA Category 6A PL

-          ISO ClassEA Ch. AMD1

-          ISO ClassEA PL 25N1513

-          TIA Category 6 Channel

-          ISO Channel Class E

-          TIA Category 5e Channel

-          ISO Class D Channel

 

For channel testing, install all patch cords prior to testing.

1.    Begin testing the installed channels with the Fluke Digital Cable Analyser and save all test results.

2.    Troubleshoot and repair any failing channels. Channels resulting in a PASS* are considered a PASS and will be acceptable for warranty.

Note: The Fluke HDTDX analyzer and HDTDR test are very helpful when troubleshooting failing channels. Both can be found on the SINGLE TEST menu & will also run automatically when a failure occurs.


8.10.4 INSTALLATION OF DATA/TELEPHONE OUTLET

Installation of outlet boxes shall be concealed.
Ensure the location of the box outlets in the site as per shop drawing /installation details once getting clearance from the civil team to do it by marker.
Mounting heights for boxes approved by the engineer as per approved mounting height details shown in the drawings.
Do the marking for the concealed box on the LGS wall by marker.
Fix the outlet boxes securely in way to be adjustable and should be located as per approved Shop drawing.
GI back coves shall be fixed on the L.G.S wall frame with necessary sports.
Plates shall be installed with all four edges in continuous contact with finished wall.
Plates shall be installed with less alignment tolerance of 1.5mm.

        INSTALLATION OF JUNCTION, PULL & TERMINAL BOXES

Fix junction, pull and terminal boxes where indicated and where required to facilities pulling of wires and cables and connection of future appliances.
Locate boxes as inconspicuously as possible, but accessible after work is completed.

8.10.5 INSTALLATION OF IT RACK:

All the installation shall be done in accordance with approved drawings, project specifications and QCS 2014.
Location/area shall be ready for site installation. Prior to the installation the area where the items to be installed shall be inspected to ensure architectural works and finishing are complete and area is free from dust.
Wall or Floor mounting of the rack should follow the instructions for the mount used and use approved installation practice appropriate for the structure and material the mount is being attached to.
Prior to the installation, check all the materials as per detail drawings and mark the location for the racks.
All the labeling of the racks and accessories shall be accordance with the IFC layout drawings.

Assembly Steps

Before performing the following steps, ensure to have a level surface that is large enough for the rack.
Should the assembly be performed on a non-level surface, the rack will not be straight once assembled.
Unscrew the hex nuts that are attached to the pillars and keep them aside.
Lay the top cover and bottom cover on a level surface.
The distance between the top and the bottom cover should be approximately the height of the rack rails.
Slide the Rack rails between the top and bottom cover and secure it with the hex nuts. Do not tighten.
Slide the second rack rail between the top and bottom cover and secure it with hex nuts. Do not tighten.
Attach the connection plate between the two rack rails on the threaded studs with the flat part of the plate facing the inside of the rack (See Figure 1). Do not tighten.

Secure the rack rails to the top and bottom cover with screws as shown in the diagram.
Flip the rack over and repeat steps 3, 4, 5, and 6.
Fixing both panels with screw & nut on the top & bottom panel.
Install the caster wheels on the bottom panel of the Racks. If required
Stand up the rack on a level surface with the bottom cover/casters facing down. Tighten all the screws.

Installing the side door panels. Press and hold the locking button available in side section of panel and fix side door into frame. Once panel is fixed release the button - Side door panel will be fixed
Fixing the Front and Rear Door. Lift the front door and insert locking into the frame hole.
Install the Thermostat Fan, installed in the top cover from outside of the enclosures/racks. The fan is kept in place using four latches and by gluing tape.
Install the bond connection from a cabinet to the cabinet door & side panel.


8.10.6 INSTALLATION OF PATCH PANELS

Copper Patch panel

Using the appropriate screws, attach the Patch Panel into the rack.

Jack could be terminated directly in the Patch Panel or in the Termination Station.
To insert a Jack in a Patch Panel engage the bottom of the jack in the opening and pivot the top latch as shown

Install Rear Cable Management Bracket
Route cables from the backside of the patch panel and loosely attach them with cable ties to the wire managing device.
Continue assembling cables in this sequence method with the Cable Management Bracket initially installed to get the appropriate length for each cable and ensure the slack of the cable is not more than 3 meters.
Secure the cable to the patch panel with a zip tie if there is a slot or tab for a zip tie.
Secure cables over the brackets with Cable Tie and ensure conductors are not damaged while testing of cable jacket with knife.
After termination of all of the cables and snapping all the jacks into the panel, gear the cable slack behind the panel and tighten the cable ties.

Label installation: affix label using edge of outer connector opening in patch panel.

 All the labeling of the Patch panels shall be accordance with the approved ICT Rack layout drawings and labeling scheme.

Fiber Patch panel

Using the appropriate screws, Install the Fiber Patch panel to the Rack with 4 Screws.
Install the patch panel in the rack mount fiber optic enclosure.
Remove the front panel of rack mount fiber enclosure, then install patch panel and fasten the screw.
Fix the equipment in the rack and leave some space between the patch panels for cables management.

Connect Single Mode / Multi Mode Optic Cables to the patch panel in one pull, which helps to protect the bend radius. Comb and bundle the   cables, and put them into the patch panel trunking, then cover it with top panels.
Secure the fiber cable into shelf with gland and there should be approximately 1 inch (2.54cm) of sheath visible at the end of the gland.  Slack of the cable is not more than 3 meters.
Secure patch panel firmly to the equipment rack or bay.
Remove the cover and Install fiber caskets and pigtails in the Fiber patch panel.
When using jacketed patch cords, use maximum cable diameter of 2.0mm and maximum connector length of 2.0 inches (from end of ferrule to end of boot).
Install the patch cords and route cables.

All the labeling of the Patch panels shall be accordance with the approved IFC Rack layout drawings

8.10.7 INSTALLATION OF POWER DISTRIBUTION UNITS

Attach the vertical-mounting brackets to the Rack PDU, using four 8- 32 flat-head screws per bracket.
Attach the Rack PDU to a vertical mounting rail in the rear of the rack/cabinets using two additional screws per bracket.
Ensure the industrial sockets type units are installed as per approved drawings and location.
Install the Industrial Plugs and Power cable for the PDU.
All the labeling of the PDU’s shall be accordance with the approved ICT Rack layout drawings and labeling scheme.

8.11 INSTALLATION OF CCTV SYSTEM

8.11.1 Installation of Fixed Pole Mount Fixed Dome Camera

·         Finalize the Light pole on which the camera to be installed as per the approved drawing.

·         Exact Location of the CCTV camera shall be as per approved CCTV installation layout plan as well and to be coordinated at site to ensure easy access for maintenance in future.

Precautions before installation

Ensure you read out the following instructions before installing the camera

·         Select an installation site that can hold at least 5 times the camera’s weight.

·         Stuck-in or peeled-off cables can cause damage to the product or a fire.

·         For safety purposes, keep anyone else away from the installation site. And put aside personal belongings from the site, just in case.

·         If the product is installed with excessive force, it may cause damage to the camera due to malfunction. Forcing assembly using non-compliant tools may damage the product.

 

Disassembling

1.    Peel off the tape fixing the camera case.

 

2.    Take off the cushion protecting the camera lens.

Installation (mount plate)

·         Attach the installation template on the desired pole surface and drill holes for screws and cables.

·         Fix the mount plate using appropriate screws.

·         Pull out necessary cables among LAN cables through the hole in the mount plate

·         Mount the bush to the camera case.

 Installing the camera module

·         Connect the LAN cable to the camera module terminal.

·         Attach the camera module to the case.

 

A magnet is embedded at the bottom of the module

Take caution not to allow any foreign objects between the attaching surfaces.

·         Adjusting the monitoring direction for the camera as per approved coverage drawings

·         Adjust the pan angle taking account of the direction to monitor.

·         Adjust the horizontal angle so that the video does not flip when rotated.

·         Adjust the tilt angle toward the direction to monitor.

Assembling the dome cover

·         Make sure to firmly tighten the fastening screws so that there is no water damage issue.

·         Mount the weather cap to the dome cover and fasten the screws.

 

8.11.2 INSTALLATION OF BULLET CAMERA

Work Procedure

·         Select a location to install the component and applicable mount as per approved CCTV drawings

·         Mark and Drill the camera mounting base on the back box.

·         Install the mount:

o   Install the Camera wall mounting base to the smooth vertical surface or GI extension bracket.

o   If necessary to prevent water damage, apply sealant around the bolt holes between the mount and mounting surface.

o   Install camera mounting base into wall bracket.

o   Pull the wires through the arm stating from the bottom of the mounting plate; pull the wires out through the threaded opening at the bottom of the arm.

o   Adjust the monitoring direction for the camera as per approved drawing.

o  

·       All active and passive equipment shall be installed in accordance with the approved drawing and manufacture’s recommendation

 

8.11.3 INSTALLATION OF PTZ CAMERA

Work Procedure

·         Finalize the Light pole on which the camera to be installed as per the approved drawing.

·         Exact Location of the CCTV camera shall be as per approved CCTV installation layout plan as well and to be coordinated at site to ensure easy access for maintenance in future.

·         Mark and Drill the camera mounting base on the pole base plate

·         Install the mounting kit of the camera in the base plate of the pole

·         Installing by wall mount

Fix the installation base with the bracket

1. Fix the base with the bracket by turning it clockwise.

1.    As shown in the picture below, gently press and lift up the handle of the hinged door on the bottom of the installation base. Please refer to the Camera Wiring Interface Board”

2.    Connect the camera safety wire to the installation base

3.    Assemble the installation base and camera by matching the installation direction guides.

4.    Rotate the mounted camera unit clockwise so that the reference indicators of top and bottom are as shown in the image

 

5.    Secure the installation base and camera using hexagon screw.

·         Pull the patch cord from the Industrial switch on the lighting pole to the camera base plate

·         Pass the cable through the base plate of the camera and connect it to the RJ45 jack of the camera

·         Adjust the monitoring direction of the camera as per approved drawing.

9.0 DOCUMENTATION

9.1 As Built Drawings

During the project completion as built drawings should submitted for client reference and record based on the red markup changes during the execution/installation stages.

9.2 System Operation & Maintenance Manual

All the used major equipment catalogue, spare parts schedule & overall project operation system will be submitted during the final handing over stage.

 

10. ATTACHMENTS

 

 


1 Comments