- Ensure that the approved and new materials have been used.
- Verify the installations are as per approved shop drawings / Details
- Ensure the Installed cable network looping is as per approved shop drawing.
- As-built marked on the drawing (Red Mark), if required.
- Check Earth pit level proper align & flushed with screed level.
- Check that the Top flange and the earth pit have been fixed
- Ensure the Adapter fixing in the top flange.
- Ensure the Cable size is as per shop drawing.
- Check clamp proper fix with earth rod with cable.
- Test Link proper fix as per installation details.
- Ensure the Equipotential Bar is installed in the correct location.
- Ensure all the Earthing cables termination with the equipotential bar.
- Check the resistance of the earth pits
- Provide Label for earth pit